Home / Case studies / Civil construction
54% fewer acknowledged findings on a civil programme
A group of civil construction contractors put Invigilo on the cameras already covering their shafts, tunnel headings and compounds. Year two came in 54% below year one.
Results at a glance
54%
Fewer acknowledged findings, year two against year one
Civil construction contractors
2 months
From first camera access to full programme coverage
Civil construction contractors
Most of the work happens where nobody is watching
Deep excavation, access shafts and tunnel headings sit tens of metres down and off any patrol route. A supervisor cannot walk a heading, a shaft and a station box in one shift.
The contractors ran several worksites at once, each with its own layout and subcontractors. Below ground the hazards change shape, and so does what a camera sees.
What was watched, and how it was set up
Every worksite already ran CCTV for security and progress photos. Nobody added a camera or pulled new cable.
What the cameras watched
- Open shafts and penetrationsPeople near edges where the drop is on the inside.
- Plant and worker separationIn a bore the gap between plant and wall can be centimetres.
- Moving exclusion zonesAreas closed during cutterhead work, segment handling or grouting, then released.
- Missing barricadesBarriers taken out for access and not put back.
- Lone workersPeople working alone where phones and wearables have no signal.
How it was set up
- Processing on siteVideo ran on a server at each site, so detection kept working when the uplink dropped below ground.
- Rules per zone and phaseAn area can be dangerous during a segment lift and ordinary an hour later, so rules switch with the work.
- Tuned on real footageUnderground scenes needed a few weeks of site footage before the thresholds were usable.
- Alerts to the area supervisorOn WhatsApp or Microsoft Teams, with the clip attached.
What changed across the programme
The number took a year to move. How supervisors worked changed much earlier.
54% fewer acknowledged findings
Second year of the programme against the first.
Faster response to what was found
The supervisor for the area heard while the work was still happening, not at the next walkaround.
Supervisors changed how they work
They act on alerts themselves, use clips in briefings, and take repeat issues to the subcontractor responsible.
What made it stick
What mattered was who got the alert and what they did with it.
It ran on every shift
Nights and weekends got the same attention as a weekday morning.
It reached someone who could act
Alerts went to the supervisor for that area, with the authority to stop the work.
It kept the evidence
Every finding has its clip, so a toolbox talk lands and a repeat issue can be traced to a crew.
It showed patterns across sites
The same problem on three headings usually points at how the work is set up.
Common questions
Did the contractors install new cameras?
No. The existing CCTV on each worksite, installed for security and progress photos, was connected over RTSP. No new hardware was needed for standard coverage.
Why did full coverage take two months?
Volume and environment. Cameras across several concurrent worksites each needed zones drawn and rules set, and underground scenes needed a few weeks of real footage before thresholds were usable.
Does detection work when the connection drops underground?
Yes. Video was processed on a server at the site, so detection and alerts kept running through connectivity gaps. With a site server, only events leave the site.
How was the 54% measured?
Acknowledged safety findings in the programme's second year were compared with the first year.
Talk to our team